'Bureaucracy frustrates NSSF investment plans'

National Social Security Fund (NSSF)'s Investment plans in real estate have stalled over the last three years due to unwieldy bureaucracy.

By Moses Walubiri

National Social Security Fund (NSSF)'s Investment plans in real estate have stalled over the last three years due to unwieldy bureaucracy, the fund's managing director Richard Byarugaba has revealed.


NSSF top management has as a result decided to invest contributors' funds in Kenyan bonds because they don't require seeking green light from a multiplicity of stakeholders, which quite often takes a long time to secure.

For NSSF to invest contributors' funds in the lucrative real estate market in Uganda, management has to get a nod from the Solicitor General, Minister of Finance, Chief Government Valuer and Public Procurement and Disposal of Public Assets.

Among projects that have been affected include Pension Towers and housing estates in Temangalo and Buloba.

"Investment in real estate in Uganda is such a hurdle because there are so many layers of offices whose approval is required yet they are beyond our control. The tendering process of these projects tend to be drawn out which makes the fund lose investment opportunities," Byarugaba said during the monthly CEO apprenticeship in Kampala.  

Byarugaba noted that such red tape makes initial cost on potential investment hard to achieve as exemplified by the stalled multibillion Pension Tower project.  

The project whose contract was signed on April 1, 2008, had its cost first shoot up from sh36b to sh120b by 2008, prompting Parliament to summon NSSF chiefs to explain. The then NSSF chairman, David Chandi Jamwa, attributed the rise to extensive changes in the project design.

But by the beginning of 2009, the cost had risen to sh147b and it is expected to shoot up to $120m (sh312b) upon completion.

The entire complex, which consists of three joint towers; two of them having 10 storeys each, and another having 23 storeys, will cover 60,000 square meters when completed.

Byarugaba had in March 2012 said the second phase was expected to be complete within three years - meaning it will be finished by 2015, but the cancellation of the tendering process early this year by the Inspector General of Government is likely to affect it.

The first phase of the project was supposed to be completed in two years, but took longer after a retainer wall collapsed on October 14, 2008, killing seven workers and leaving scores injured. The construction was supposed to begin on April 1, 2008 and end by at least May 2010.

But after the tragedy, the works dragged on up to January 2012 when Roko completed the first phase.