Uganda seeks new contractor for sh112b Kabale-Bunyonyi road works

Siraj told Parliament that the Ministry of Works is engaging the Attorney General to pave the way for a new contractor. During plenary (November 18, 2026), the minister said that “the contractor has disappointed us."

Minister of State for Works, Musa Ali Siraj, speaking during the plenary session. (Courtesy photo)
By: Mary Karugaba and Dedan Kimathi, Journalists @New Vision

________________

Government is moving to terminate its contract with Egyptian construction firm Samcrete Egypt Engineers and Contractors over failure to commence construction of the Kabale–Lake Bunyonyi Road, the Minister of State for Works, Musa Ali Siraj, has told Parliament.

Siraj told Parliament that the Ministry of Works is engaging the Attorney General to pave the way for a new contractor. During plenary (November 18, 2026), the minister said that “the contractor has disappointed us and the ministry is working with the Attorney General to see how we can terminate the current contract and get a new contract,” Siraj said.

His statement followed concerns raised by Deputy Speaker Thomas Tayebwa, who questioned why the 15.8-kilometre road project, which he commissioned in June 2025, had not registered meaningful progress despite its importance to tourism and economic development in the Kigezi sub-region.

Tayebwa said residents had repeatedly questioned him about the project, accusing him of commissioning a road that had not materialised.

“People are saying I launched air. The President (Yoweri Museveni) will be in Kabale soon, and people are going to report me that i launched air,” he said, demanding an explanation from the Ministry of Works on the contractor's failure to deliver.

The sh112b infrastructure project comprises the Kabale–Lake Bunyonyi Road and the Kisoro–Mgahinga Road. It is intended to improve access to Lake Bunyonyi, one of Uganda's leading tourist destinations, while facilitating trade, investment and movement of people in the region.

Tayebwa lamented that although the African Development Bank (AfDB) agreed to finance the project, the company had failed to mobilise adequate manpower and equipment to undertake and complete the works. He said the matter had been reported to the AfDB, which had commenced investigations to establish what went wrong with the procurement and implementation arrangements.

The proposed termination comes amid wider concerns about delays in infrastructure projects in the Kigezi sub-region, including the construction of two ferries intended to improve transport and safety on Lake Bunyonyi.

Where are the ferries?

While raising issues of National Importance, Rubanda County West MP Bruce Balaba Kabaasa told Parliament that the delivery of the two ferries had repeatedly been postponed, with the original completion deadline of 2024 shifted to 2025 and subsequently to December 2026.

Kabaasa said he had visited the ferry construction site three days before the parliamentary sitting but found no evidence of ongoing work.

“There is literally no work going on with the construction of the ferries,” he reported to the August House. The MP questioned how the Ministry of Works expected to meet the December deadline when construction activities were seemingly not taking place.

In response, Siraj said the ministry would ensure the ferries were completed by the end of December. He invited Kabaasa to meet the project team at his office at the ministry for updates. However, Tayebwa questioned the usefulness of holding meetings in ministry offices when the concerns raised by the MP related to the absence of work at the construction site.

“Now under AC, what is he going to see?” Tayebwa asked, insisting that ministry officials should account for the project on the ground. “The MPs are representing people. The people need to see you on the ground,” he quizzed.

Ali proposed that the MP first meet the project team at the ministry before arrangements were made for a site visit.   Tayebwa subsequently directed that the engagement should follow that sequence, with the ministry meeting coming first and a visit to the construction site thereafter.

The concerns over delayed infrastructure projects were compounded by reports of deaths on Lake Bunyonyi, where Kabaasa said about 11 people had drowned between July and November 18, 2026. The MP told Parliament that some of the deaths could have been avoided if marine police had been adequately facilitated to respond to emergencies.

He said marine police officers had sometimes failed to respond to distress calls because they lacked fuel for their boats. Kabaasa called on government to provide fuel to support emergency rescue operations and prevent further loss of life on the lake.

The Minister of Internal Affairs, Prof. Ephraim Kamuntu, acknowledged that some police and marine stations across the country experienced fuel shortages, saying government was addressing the funding challenges.

However, Tayebwa asked the minister to establish whether fuel shortages were indeed responsible for the failure by marine police to respond to emergencies on Lake Bunyonyi.

Kamuntu clarified that his acknowledgement of fuel shortages was general and did not necessarily mean that lack of fuel was the specific reason for the failure to respond to incidents on the lake.

He said other circumstances could have contributed to the delayed responses.