Ministries on the spot over inflated procurements

On oil development, the Auditor General warned that delays in key projects threaten Uganda’s target of first oil production by mid-2026. He said that project completion rates stand at 61.3% for Tilenga Project against a target of 73.18%.

Fort Portol Hospital. Five regional referral hospitals; Hoima, Jinja, Mubende, Fort Portal and Kabale lacked reliable power backup systems, affecting installation and operation of intensive care unit equipment, oxygen plants and diagnostic machine.
By: John Odyek, Journalist @New Vision


KAMPALA - The Auditor General (AG), Edward Akol, Thursday released the 2024/25 annual audit report, with a major highlight being the persistent inflation of the costs of goods