________________
Works on the 29.72km Luwero–Butalangu Road, a key road in the greater Luwero Triangle, is in its final stages of completion, with the project now at 84.8% physical progress.
The upgrade of the Luwero-Butalangu Road is among the outstanding pledges in the area for the contribution made to the National Resistance Army war of 1981-1986, which ushered President Yoweri Museveni and the National Resistance Movement (NRM) government into power.
On Wednesday, officials from the Ministry of Works and Transport conducted a site visit and revealed that construction works are substantially complete across most sections of the road, with over 26.8km already done.


In his letter to the Speaker of parliament, Ssekabira said despite the completion date of the project set for August 16, 2026, there were no signs that the work will be expedited; several sections of the road were still closed and incomplete.
“Right Honourable Speaker, specifically the section between Kiwoko and Luwero Don-fuel station has been closed by the contractor for now one full year hence no access by motorists,” Sekabira argued.
However, the Ministry of Works and Transport explained that land acquisition had constrained progress for some time. But the Ministry settled the outstanding land compensation in June 2026, clearing the way for the project to proceed to completion.
The ministry noted that the fuel station previously flagged as a sticking point had also been compensated.
The Ministry noted that they had a challenge of some PAPs not coming forward to receive their payments, saying the funds are available, and their compensation team will be visiting the project area to trace and pay them.
The project is jointly funded by the Arab Bank for Economic Development in Africa, the OPEC Fund for International Development and the Government of Uganda.