Karenga road works under scrutiny as minister orders recovery of Sh700m

Alum said the work did not match the amount spent. She said some sections that were supposed to be fully graded were left untouched, and culverts and other construction materials were lying unused along the road. “Out of the sh1b, sh700m went for this road. But when you see the quality of work done, there is no value for money. The culverts are lying there, and a number of materials are lying beside the road,” she said.

The inspection team found sections affected by waterlogging, alongside poorly executed drainage works.
By: John Masaba, Journalist @New Vision


KARENGA - The Government has ordered the recovery of Sh700m spent on substandard road works in Karenga District after an inspection found poorly constructed drainage structures, unfinished sections and construction materials abandoned at the site.

Sandra Santa Alum, the Minister of State for Economic Monitoring, issued the directive after her team inspected the Karenga-Kakuanga-Morinyang road on November 16. The road works reportedly received Sh700m out of the Sh1b road maintenance grant extended to the district.

Alum said the work did not match the amount spent. She said some sections that were supposed to be fully graded were left untouched, and culverts and other construction materials were lying unused along the road.

“Out of the sh1b, sh700m went for this road. But when you see the quality of work done, there is no value for money. The culverts are lying there, and a number of materials are lying beside the road,” she said.

The district roads committee had instructed the contractors and technical staff responsible for the project to return to the site and correct the defects. They were also warned that administrative action would follow if the work was not improved. (Courtesy Photos)

The district roads committee had instructed the contractors and technical staff responsible for the project to return to the site and correct the defects. They were also warned that administrative action would follow if the work was not improved. (Courtesy Photos)



The minister also questioned why cement bought for the project had been left exposed to weather, causing it to deteriorate instead of being used for construction.

The inspection team found sections affected by waterlogging, alongside poorly executed drainage works.

Alum said the engineer responsible for supervising the project should be held accountable for the defects.

"I was happy that he has been interdicted, but the question is: where is the money? Because the people who were supposed to benefit from this road are still waiting for the services," she said.

She directed the district Chief Administrative Officer (CAO) to pursue the recovery of the money from those responsible for the poor execution of the project.

"Secondly, I have tasked the CAO to make sure that this money is recovered because the people who mishandled this work are there. They are not dead," she said.

Napore West County MP Fidelis Loluk Logwee said the road had previously been examined by the district roads committee, which recommended that those responsible for the poor work be held accountable.

Logwee expressed disappointment with the quality of the drainage structures and materials used, saying the work fell short of the Government's commitment to improve road access across the country.

Alum said the engineer responsible for supervising the project should be held accountable for the defects.

Alum said the engineer responsible for supervising the project should be held accountable for the defects.



"This has been a National Resistance Movement government commitment to make sure there is good access and road infrastructure in every district. But this afternoon, I am a little bit disappointed that there has been shoddy work on the road, particularly the drainage structures are not constructed well," he said, adding, “I think even the materials being used on the road are not of good quality.”

The state minister for Ethics and Integrity, Rose Lilly Akello, said the road had been inspected about a month earlier, when they identified defects and directed district leaders to ensure they were corrected.

She said the earlier inspection found that culverts had not been properly installed, offshoots were missing, and murram works had not been adequately done.

"One month ago, we moved out to the field where we have just gone today, and it was a mess. We directed the Chief Administrative Officer to handle the issues we identified," Akello said.

The district roads committee had instructed the contractors and technical staff responsible for the project to return to the site and correct the defects. They were also warned that administrative action would follow if the work was not improved.

However, Akello said the latest inspection showed that little had changed.

"For God's sake, sincerely, there was no value for money. You have even seen it as the media. I pray that the law takes its course and those responsible are apprehended, or they put back the money into the road so that we can get value for money," she said.

Akello said the road was important to local communities and also provides access to areas visited by tourists to view wildlife.