The Namutumba deputy Resident District Commissioner (RDC) has rebuked officials over spending shillings 30 million on the construction of a two-classroom block, describing the cost as “exaggerated and unacceptable.”
The RDC's rebuke also included building contractor Kirongo United Investment. The construction of the classroom block is being funded under the development grant aimed at addressing congestion and improving learning conditions.
During a tense meeting, deputy RDC Richard Musana openly criticised the district officials, expressing that they have caused enough frustration during the monitoring and launching exercise at the project site.
The RDC questioned the procurement process and demanded a detailed breakdown of expenditures, including contracts awarded, bills of quantities (BOQ’S) and comprehensive documentation about the project.
“I am not convinced that shillings 30 million was only spent on the construction of a foundation for a two-classroom block, this doesn’t reflect value for money, and taxpayers deserve proper accountability and transparency in the use of public funds,” Musana said.
He said regarding their inability to provide a satisfactory explanation for the utilisation of the funds for the construction of only a two-classroom block foundation at Bubutya Primary School in Bulange sub-county in Namutumba district, the civil servants must ensure that every shilling allocated to education improves service delivery, not just inflated costs.
District officials attending the meeting.
Musana, who demanded value for money, said he wasn’t convinced with the utilisation of the funds, saying the matter is now referred to the Anti-Corruption Unit.
Misplaced documents
"You requested that I launch the second phase, yet you have failed to provide the Bill of Quantities (BQ) documents for this project. It is truly disconcerting," Musana said.
He explained that, according to the Local Government Act (1997) and Public Procurement and Disposal of Public Assets Act (2003) mandate community involvement and transparency in project implementation.