West Nile to get 5 megawatts dam
Publish Date: Jul 30, 2012
West Nile to get 5 megawatts dam
Minister D’Ujanga (Middle) with the contractors at the site. PhotoBy Benedict Okethwengu
  • mail
  • img
newvision

By Benedict Okethwengu

With the much-awaited 3.5 megawatts Nyagak mini-hydro dam in Zombo district yet to be switched on, tomorrow (Tuesday) to salvage the people of West Nile from insufficient thermal power  supplied by West Nile Rural Electrification Company (WENRECO), works on the 5 Megawatt second mini hydropower dam on the same river has kicked off.

Simon D’Ujanga, the state minister for Energy and mineral development  told New Vision on Sunday that ,the 5-megawatt Nyagak II dam is  being built downstream the Nyagak River, at Rateng village, in Paidha sub-county about 10  kilometers from the first Nyagak dam.

D’Ujanga explained that Nyagak II mini hydro power dam is to boost Nyagak I whose 3.5-megawatt capacity is not enough to power the whole of West Nile region.

 “Construction of Nyagak II mini-hydro power project has started with the construction of an access road to the site and I have asked Spencon services to take some of their equipment to the new site,” he said.

“We have the resources available for Nyagak II mini-hydro power dam which will boost Nyagak I and we are in the process of connecting West Nile to the national grid,” D’Ujanga said.  

He however did not disclose how much Nyagak II project would cost the government for whose construction will be complete in three years.

He revealed that part of the power supplied by Nyagak would be extended to Mahagi and Aruu in Democratic Republic of Congo.

“We have received request from Mahagi and Aruu demanding for our power but we are yet to consider it,” he said.

He also said that government is waiting for approval from KfW, the German Development Bank for the massive kick off of the distribution of power lines in the region.

He noted that it would take about a year for the all the districts in West Nile to fully connected.


 

The statements, comments, or opinions expressed through the use of New Vision Online are those of their respective authors, who are solely responsible for them, and do not necessarily represent the views held by the staff and management of New Vision Online.

New Vision Online reserves the right to moderate, publish or delete a post without warning or consultation with the author.Find out why we moderate comments. For any questions please contact digital@newvision.co.ug

  • mail
  • img
blog comments powered by Disqus
Also In This Section
Cleaner low sulphur fuel diesel on market
Effective February 2, 2015, low Sulphur fuel diesel with 50 parts per million (ppm) sulphur content will be on market....
Electricity tribunal hits snag over absence of energy ministry PS
Hearing at the electricity disputes tribunal in the row between Umeme and ERA hits a snag over the absence of Energy ministry PS Kaliisa Kabagambe....
Honda investigating possible exploding airbag death
Honda is probing a deadly crash in the United States possibly linked to exploding air bags blamed for killing at least five people....
Contradictions cloud pensions liberalization
MAJOR contradictions still exist among the major backers of the impending liberalized pensions sector on which to adapt with the liberalization bill expected on the floor of parliament...
Gov
IN efforts to expand market for Uganda's agricultural produce, Government has embarked on wooing more investors in agro-processing to set up investments...
Stanbic Bank signs debut $85m  loan
Stanbic Bank Uganda (SBU) has signed an $85 million, 18-month loan to fund its general business activities, the first time it has borrowed from international loan markets, the main arranger of the facility said...
Do you agree with the new tax on private schools?
Yes
No
Can't Say
follow us
subscribe to our news letter