Bujagali cost remains at $860m

Dec 17, 2010

THE cost of the 250MW Bujagali Hydropower Project will remain at $860b and not reach the $1b mark, project stakeholders have clarified.

By Ibrahim Kasita

THE cost of the 250MW Bujagali Hydropower Project will remain at $860b and not reach the $1b mark, project stakeholders have clarified.

“This is because there is a contingency sum provided for within the overall project costs to cater for changes in price,” a source familiar with the dam financial operations said.

The clarification allayed fears that the project costs would go above the $1b as the multi-donor funded project encountered poor ground conditions which required extra work to ensure the integrity of the dam. The project is expected to be fully commissioned by April 2012.