Ntungamo Road to delay

By Vision Reporter

Added 14th February 2003 03:00 AM

Upgrading and gravelling of Mbarara-Ntungamo Road by Roko construction and NICONTRA Contractors at sh350m, is to delay for another six to eight months

By Vision Reporter

Upgrading and gravelling of Mbarara-Ntungamo Road by Roko construction and NICONTRA Contractors at sh350m, is to delay for another six to eight months and the original agreed money will double, due to base failures in the construction of the first 30km from Mbarara Town.

This was revealed by the engineer incharge of Mbarara station, Silver Byarugaba, during the tour of the road recently.

Work is financed by the Government.