Minister Byabagambi grilled over sh1bPublish Date: May 01, 2014
Minister Byabagambi grilled over sh1b
  • mail
  • img
Minister John Byabagambi
newvision

By Umaru Kashaka    

Legislators on the physical infrastructure committee have grilled the works state minister John Byabagambi over sh1.2b that was paid to the M&B Engineering Company to construct Birara Bridge linking Rukungiri to Kanungu districts.


The committee was considering ministry’s sh2.5 trillion budget request for 2014/15 financial with officials from Uganda National Roads Authority (UNRA).

The MPs noted that a certificate of completion was given to the contractor when less than 20% of the work had been done.

“This bridge was going to be a lifeline for our people as it was going to link Kanungu with other surrounding areas. Why did you pay this contractor sh1.2b for work not executed? This caused government loss because this money would have been put to better use,” committee chairperson Ephraim Biraaro noted.

The committee also queried sh31b that was paid in cost for constructing Fort Portal-Bundibugyo-Lamia Road, saying the cost would have been avoided if proper contract management procedures had been followed.

“They go on to compensate people even where it’s not necessary. How can you compensate people on road reserves that belong to government?” the Busongora County North MP William Nzoghu asked.

The minister admitted that the contractor abandoned the work at Birara Bridge, but said four of his staff who connived with the contractor to have a certificate of completion issued to him has since been interdicted.

“It’s true this contractor abandoned the work and I hear he is in South Sudan. But the ministry did its part administratively to prosecute these individuals (names not revealed) who colluded with the contractor and a certificate was issued. I don’t know how far the prosecution has gone, but they were prosecuted,” Byabagambi said.

The construction of Birara bridge was previously started by the ministry of works, but in December last year UNRA signed a sh13b contract with China Harzone Industry Corp for its construction under a design and build scheme after the first contractor abandoned the site.

It will be a seven-meter bridge with pedestrian walkways on either sides, built with both steel and reinforced concrete.

 

The statements, comments, or opinions expressed through the use of New Vision Online are those of their respective authors, who are solely responsible for them, and do not necessarily represent the views held by the staff and management of New Vision Online.

New Vision Online reserves the right to moderate, publish or delete a post without warning or consultation with the author.Find out why we moderate comments. For any questions please contact digital@newvision.co.ug

  • mail
  • img
blog comments powered by Disqus
Also In This Section
A French lawyer said he had lodged a complaint at the International Criminal Court on behalf of the Palestinian justice minister accusing the Israeli army of "war crimes"...
South Africa to host 2016 AIDS conference
South Africa''s port city of Durban will host the 21st International AIDS Conference in 2016, marking the forum''s return to Africa after 16 years....
8 pupils struck dead by lightning in Bushenyi
THE shocking incident happened at 4:45 PM during a simple drizzle, as the pupils were in class for evening lessons at the school...
Makerere agrees to clear staff allowances
Makerere University has agreed to pay staff allowance arrears for the month of May, amounting to sh3.7b....
Govt to pay all salary arrears by September
THE Secretary to the treasury Keith Muhakanizi has promised that all salary arrears for civil servants will be paid by September...
Air Algerie said it lost contact with one of its passenger aircraft nearly an hour after takeoff from Burkina Faso on Thursday bound for Algiers....
Should government review powers of kings?
Yes
No
Can't Say
follow us
subscribe to our news letter