Allocate Bujagali 50MW to industrial sector-UMA
Publish Date: Feb 05, 2012
  • mail
  • Big font Small font
  • clip
    Prime Minister Amama Mababazi inspecting part of the dam. PHOTO by Enock Kakande

    By Vision Reporter

    Uganda Manufacturers Association (UMA) has asked government to direct the 50 megawatts from Bujagali hydro-power project to the industrial sector.

    The Executive director Uganda Manufacturers Association, Kigozi Sebaggala said the industrial sector has 100MW deficit of electricity supply.

    “This is to ask government to consider our request. If the 50MW is directed to our sector, that will help to reduce the cost of production,” Sebaggala told New Vision in an interview on Friday.  

    Prime Minister Amama Mbabazi on Thursday witnessed the first delivery of 50MW.

    It was part of the many mandatory tests the turbines will undergo before the official launch of the entire 250MW project in July.

    There are five turbines and each can produce 50MW. However , the electricity generated during the testing process is connected to the national grid for consumption.

     

  • |
  • Share
  • |
  • |
  • |
  • mail
  • |
  • img
blog comments powered by Disqus
Do you think educated women are more promiscuous than men?
YES. The poll is spot on
NO. The poll is flawed
Promiscuity is not for a particular sex