UNRA misappropriated sh4 trillion, 90 face prosecution

May 26, 2016

President orders IGG, CIID and AG to jointly follow and quickly have the culprits prosecuted.

President Yoweri Museveni has received the final 1,300-page report from the Commission of Inquiry into the Uganda National Roads Authority.

Lady Justice Catherine Bamugemereire (Court of Appeal), who led a six-month probe, presented the Report to the President.

Highlights:

* Shs9 trillion used by UNRA to construct 1,500km of roads in 7 years...funds were enough to construct at least 5,147km.

* Shs4 trillion was misappropriated by the old UNRA team.

* Commission recommends the prosecution of over 90 people as well as assets recovery.

* President orders IGG, CIID and AG to jointly follow and quickly have the culprits prosecuted.

 